6950 Taylor Drive
17 février 2026
RéussiAucune infraction trouvée
Ce restaurant a été inspecté 12 fois depuis le 18 juin 2024, avec 12 réussites et 1 fermeture au dossier.
Wet reusable wiping cloths were laying on the counter and not in a container of sanitizer solution as required. These wiping clothes were put in the laundry to be washed. , A new sanitizer container of 100 parts per million chlorine was made and clean wiping clothes used.
Hot holding Temperature of a pot of gravy on the stove without any heat source was found to be at 30 Celsius with an infrared thermometer and when stirred and checked again the temperature was 48 Celsius. , High risk food items such as gravy must not fall into the temperature danger zone - (from 4 c to 60 C). To be kept above 60 C or held below 4 C. This pot of gravy was discarded at time of inspection., , Cold storage unit temperatures were found to be within correct range., Containers were found to be labeled and covered and meat stored separately from other food items.
Ce dossier provient d'Alberta Health Services Environmental Public Health, qui inspecte les établissements alimentaires partout en Alberta. Les inspecteurs notent toute infraction aux règlements sanitaires applicables à chaque visite. Le résultat ci-dessus correspond à la dernière inspection au dossier.
L'Alberta enregistre chaque visite soit comme une inspection routinière (avec d'éventuelles infractions notées), soit comme un ordre de fermeture. Si vous voyez des infractions listées sans ordre de fermeture, l'exploitant a été autorisé à poursuivre ses activités tout en les corrigeant. Un ordre de fermeture signifie que l'inspecteur a exigé l'arrêt du service à la clientèle jusqu'à la correction des problèmes.
Cutting boards were stored in a manner that may not allow for proper drying. Some cutting boards were tight against each other., Ensure cutting boards are stored in a rack with enough space for air flow around each cutting board, , Purchase additional racks if needed, , Correct by Feb 17 2026
Thorough cleaning is needed the prep area and the dishwasher area. The sinks next to the dishwasher have a heavy layer of calcium buildup. The dish wash counters and the walls below and above the dishwasher and the floor require thorough cleaning. Also areas and items such as the door to the dining area next to the dish pit, the inside and outside of coolers and freezers, the walls and floors behind and below the stainless-steel prep counters and hot holder unit and the cooking equipment and area around it. , , A previously worn used black apron was laying on the food prep counter. The apron was removed and put in the laundry at time of inspection. Aprons and other contaminated items cannot be in contact with food preparation areas and food contact services. , , Cleaning to be completed by Tue Feb 17 2024.
The following area needs to be cleaned:, - Ice machine (from inside), - Exhaust filters and surrounding area over the oven, Please ensure the indicated areas are maintained in a clean and sanitary condition., , COMPLETED: - Fryer area (behind and hard-to-reach) and Grill area (behind and hard-to-reach)
There was a container in the all-purpose flour with no handle being used as a scoop. , , After the conversation with the supervisor, the container was removed. , , Please ensure scoops with handles are being utilized for bulk foods, and ensure scoops are either stored outside or in a manner that the handle does not come in contact with food.
The following area needs to be cleaned:, - Fryer area (behind and hard-to-reach), - Grill area (behind and hard-to-reach), - Ice machine (from inside), - Exhaust filters and surrounding area over the oven, , Please ensure the indicated areas are maintained in a clean and sanitary condition.
email Correspondence from Angie from July 10 2024., , Hi bryon – the start of replacing our countertops started today. – I will let you know when the subset is built and when we are installing
Correspondence with Angie on June 28 2024., , I spoke with Angie on the phone and she informed me that work will start on the installation of new countertops on July 4 and is expected to be completed by July 11, ,
Email received from Angie on June 17 2024., , Sorry for the late update however we are still in limbo mode on getting a color match for the laminate. We have told them to not worry about a color match. Now we are waiting for an ETA in the next available laminate., , Reply, Thank you for the update. I was going to call you to see where things were at when I saw your email. Please let me know the ETA when you find out. Thanks again, , Bryon, ,